Skip Links

Steel Essentials - A guide to steel construction - Click to go to homepage [Access Key '0']
 

Economics & Programme

The steelwork requirements for a project usually develop in three stages: scheme; structural frame design; detail design.

In three parallel stages, the cost plan develops from budget/guide price through tender/contract to final account. Often quantity surveyors, general contractors and steelwork contractors will use the overall tonnage of steel in the structure as the basis for estimates and bills of quantities. There are dangers in this approach if the structure is unusual, but databases of tender prices linked to types of work are published. Similarly regularly published surveys of steelwork contractors give guidance on programme. Programme periods include two elements: off site lead-in needed to procure steel, produce details and fabricate the steel components; and the on-site period for erection.

Information Sources:

Contact details for further information and guidance:

Corus
Construction Services & Development,

T. +44 (0) 1724 405 060
www.corusconstruction.com

The British Constructional Steelwork Association Ltd.,

T. +44 (0) 207 839 8566
www.steelconstruction.org

BCSA’s Member Companies are also available for advice and may be approached directly using the contact details on the BCSA website.

Did you find what you wanted?